Pasco's $7.1 million deal for Meritage Homes to widen Old Pasco Road to four lanes was pulled Nov. 17 over a notice error. It is set for Dec. 8.

Updated Nov. 17: the deal did not come to a vote Tuesday. County staff told commissioners that Meritage had incorrectly noticed the development agreement, and asked for it to be continued to the Dec. 8 commission meeting at 1:30 p.m. in New Port Richey, according to the meeting video.

Another stretch of Old Pasco Road north of Overpass Road would be widened from two lanes to four under a deal Pasco County commissioners are due to take up Dec. 8. Meritage Homes of Florida would design, permit and build the road, and the county would pay it back in cash.

The county estimates the reimbursement at $7,140,000. The money is already in the county’s capital improvement plan for the 2027 budget year, county staff said in the agenda memo for the Nov. 17 meeting.

Where the new lanes would go

The widening would start just north of the intersection of Old Pasco Road and The Coyote Way, at Sedgeway Boulevard. It would end just north of Old Mill Road, where the road narrows back to two lanes. That is the route shown in the agreement’s map exhibit. Final engineering will be set at permitting, the map says.

It is the next piece of a longer job. County staff said:

  • Old Pasco Road from about Sonny Drive to Coyote Way and Sedgeway Boulevard is being widened to four lanes now.
  • The section from Post Oak Boulevard to Sonny Drive is programmed in the county’s 2028 capital plan.
  • The Meritage section, north of Coyote Way, adds road work “not currently contemplated” in the county’s capital plan, the memo said. The reimbursement for it is budgeted for 2027.

What the road would get

The memo lists the road’s planned cross section:

  • four 12-foot travel lanes
  • two 5-foot bike lanes
  • a 22-foot median
  • a 6-foot sidewalk on the east side
  • a 12-foot multi-use path on the west side

Why a homebuilder is building it

Commissioners approved the Old Pasco Road MPUD on May 6, 2025, the memo said. The rezoning allows 106 townhomes on about 18.36 acres. One of its conditions required the developer to sign a development agreement to widen this stretch of Old Pasco Road for cash reimbursement.

The county would repay only the road work. Meritage’s own access, including a southbound left-turn lane into the townhomes, is excluded from the reimbursement, the agreement says.

The agreement also says the townhomes’ permits, plats and certificates of occupancy cannot be held back because of the road. Homes can be built and sold without waiting for the widening, as long as Meritage keeps to the agreement.

The timeline

Under the agreement, Meritage must:

Step Deadline
Start design Within 90 days of the agreement taking effect
Apply for all permits Within 12 months of the agreement taking effect
Finish construction Within 24 months of getting all permits

The agreement takes effect when it is recorded in the county’s public records, after commissioners sign it.

The county says it already owns the right of way for the road itself. It does not yet own the land needed for drainage ponds. The county must get that land from the Pasco County School District within 90 days, at no cost to the builder, the agreement says.

What it means for you

  • Nothing changes on the road yet. Design starts only after the agreement is signed and recorded. Construction would follow permits, which could take up to a year.
  • The vote is now set for Tuesday, Dec. 8. County staff asked for the item to be continued to the 1:30 p.m. public hearings that day at the West Pasco Government Center, 8731 Citizens Drive, New Port Richey. It was pulled Nov. 17 because the developer’s public notice was incorrect. The public can comment on each public hearing item, the county’s Nov. 17 agenda says.
  • Watch from home. The meeting is broadcast live on the county’s website and YouTube channel, on Frontier Channel 42 and on Spectrum Channel 643.
  • Questions about the deal go to Pasco County Planning, Development and Economic Growth, which wrote the memo (file PDE27-0036).

For other work on the main roads around Wesley Chapel, including the Interstate 75 Exit 279 ramp and State Road 56, see our road construction and closures page.