Pasco County will share its data center research at a public workshop Tuesday, Dec. 1, in Land O' Lakes. The county's moratorium covers Wesley Chapel.

Pasco County will show residents what it has found so far about data centers at a public workshop Tuesday, Dec. 1. The research is being done while the county’s temporary ban on new data center applications is in force, and that ban covers Wesley Chapel.

The workshop runs 5:30 to 7:30 p.m. at the Land O’ Lakes Recreation Complex, 3032 Collier Parkway, about eight miles west of Wesley Chapel. The county announced it in a Nov. 18 release.

What the workshop covers

The county’s Planning, Development and Economic Growth Department is running it with Florida State University’s Barnebey Planning & Development Lab. The release lists five research areas:

  • electric use and grid capacity
  • water use and cooling methods
  • environmental and wildlife concerns
  • economic impact and revenue
  • sound and vibration

Visitors move between three stations. One covers the county’s findings, one covers how other communities handle data centers, and one collects residents’ questions, concerns and priorities. The county said that feedback “will help inform Pasco’s ongoing research and future data center regulatory efforts.”

The moratorium behind it

County commissioners adopted the moratorium by a roll call vote on July 14, 2026, according to the meeting minutes. The county’s release says the pause began May 27, 2026. That is the date the ordinance was first advertised for a public hearing. On June 16, commissioners applied Florida’s pending ordinance doctrine to it, the ordinance says.

Under the ordinance, file PDE26-0777:

  • The county will not accept applications for building permits, site plans, rezonings, development agreements or comprehensive plan changes tied to data centers, large-scale data centers or other “large load customers.”
  • It applies across unincorporated Pasco, which includes all of Wesley Chapel. Wesley Chapel has no city government, so county rules decide what can be built here.
  • Server and computer rooms using no more than 2.5 megawatts, housed as a side use at a business, are exempt.
  • It lasts up to 12 months, unless commissioners repeal it sooner or extend it by resolution.

The ordinance says such facilities need “substantial water resources for cooling systems and substantial electrical power.” It says Pasco relies heavily on groundwater from the Floridan Aquifer. It also says the county has no zoning rules written for data centers yet. The moratorium is meant to give staff time to draft them. A 2026 state law, Chapter 2026-65, lets counties regulate such sites and lets local governments prohibit large-scale data centers.

What it means for you

  • Go and ask. The workshop is the public’s chance to question county staff and the FSU researchers before rules are drafted. The release does not say registration is needed.
  • Can’t make it? The county has not said whether the findings will be posted online.
  • Nothing can be filed for now. No data center application can be submitted for land in Wesley Chapel while the moratorium is in force.

Any permanent rules would go to public hearings before the Planning Commission and the Board of County Commissioners. Meeting agendas are posted on the county’s CivicClerk portal.