Pasco County is designing a traffic signal where Chapel Pines Boulevard meets Curley Road. Construction is planned for April to October 2027 at about $1.5 million.

Pasco County is designing a new traffic signal for the intersection of Curley Road and Chapel Pines Boulevard in Wesley Chapel. The county expects to build it between April and October 2027.

Overview

The signal is in its final design stage. County staff estimate construction at $1.5 million, with work planned from April 2027 to October 2027. Those dates and costs are estimates, the county’s project memo says.

The schedule comes from a county change order filed in the agenda packet for the Pasco County Commission’s Nov. 17 meeting, item N112. It goes to commissioners Tuesday as a noted item, to be received and filed, so no vote is needed.

Where the project stands

Coastal Design Consultants Inc. started designing the signal in April 2026, under an existing engineering contract with the county. The task order is capped at $99,950.

The design was due to be finished Oct. 11. The county has given the consultant 30 more days, moving the completion date to Nov. 10, at no extra cost. Staff said the consultant needed more time to finish structural calculations and work in the county’s review comments before the final plans.

The county’s project memo sets out the phases:

Phase Planned start Planned finish Estimated cost
Design and post-design services April 2026 November 2026 $99,950
Construction April 2027 October 2027 $1,500,000
Construction engineering and inspection (county staff) April 2027 October 2027 $75,000
Total $1,674,950

The money is in the county’s capital plan. The plan’s signal list, also in the packet, shows $150,000 for the Curley Road and Chapel Pines Boulevard signal in the 2026 budget year and $1.5 million in 2027.

What the signal will look like

The intersection has three legs. Overhead distribution and transmission power lines run along the east side of Curley Road, so the designers are limited in where poles can go. The design scope gives two options:

  • one mast arm on the west side of Curley Road, carrying signal heads for all three legs
  • a mast arm on the west side for Curley Road traffic, plus two signal heads on pedestals on the east side for Chapel Pines Boulevard traffic

The work also covers new signs, pavement markings and lighting at the intersection.

What it means for you

  • Nothing changes at the intersection yet. The signal is still being designed, and the county has not yet hired a contractor to build it.
  • Construction is planned for April to October 2027. The county has not published lane closures or a detour for that work. We will report them when it does.
  • Questions about the project go to Pasco County’s Transportation Engineering Department, which runs it. Its project management office is at 727-834-3604.